Gestão & Produção
https://www.gestaoeproducao.com/article/doi/10.1590/1806-9649-2023v30e5923
Gestão & Produção
Original Article

Analysis of preventive maintenance strategy in off-road trucks

Análise de estratégia de manutenção preventiva sistemática em caminhões fora de estrada

Adriane Freire Souza Silva; Elizeth Cristina Silva Santos; Rosana Maria do Nascimento Luz; Rafael da Silva Fernandes

Downloads: 1
Views: 177

Abstract

Abstract: Preventive maintenance is an important strategy to improve physical availability, reduce downtime and extend equipment life. In the context of mining, transport fleets are large equipment and are subject to unplanned events that, in turn, interrupt operation and lead to unavailability. Therefore, the objective of this work is to analyze the main causes that influence the throughput of performance indicators of truck maintenance, focusing on the measurement of impacts caused by inefficiency of preventive maintenance. Thus, the data of 118 trucks were collected in 2022 and the performance calculated. The fleet CAT® 797F was prioritized was not adherent to the programmed, resulting in a production loss of 5,086,957   t o n s and, for maintenance, an unavailability was 9,722.88 h and 3,870 failures. Two evaluation requirements were proposed focusing on evaluating the notes and analyzing the adherence to the preventive. In summary, it was found that of the 783 scheduled preventive maintenance only 607 were performed and presented problems related to compliance with the guidelines. Finally, the inefficiency of the preventive ones generated an increase of more than 819 failures and an impact in the availability of 8.16%.

Keywords

Reliability, Productive performance, Management maintenance, Mining processes

Resumo

Resumo: A manutenção preventiva é uma estratégia importante para melhorar a disponibilidade física, reduzir o tempo de inatividade e prolongar a vida útil dos equipamentos. No contexto de mineração, as frotas de transporte são equipamentos de grande porte e estão sujeitos a eventos não planejados que, por sua vez, interrompem o funcionamento e acarreta a indisponibilidade. Isto posto, o objetivo deste trabalho é analisar as principais causas que influenciam no desempenho dos indicadores de performance da manutenção dos caminhões, em particular, com foco na mensuração dos impactos causados pela ineficiência da manutenção preventiva. Desta forma, os dados de 118 caminhões foram coletados em 2022 e a performance calculada. A frota CAT® 797F, priorizada, não foi aderente em relação ao programado, acarretando numa perda produtiva de 5.086.957 toneladas e, para a manutenção, numa indisponibilidade foi 9.722,88 h e 3.870 falhas. Dois requisitos de avaliação foram propostos com foco em avaliar os apontamentos e analisar a aderência à preventiva. Em síntese, foi constado que das 783 manutenções preventivas programadas apenas 607 foram executadas além de apresentarem problemas relacionados ao cumprimento das pautas. Por fim, a ineficiência das preventivas gerou um aumento de mais de 819 falhas e um impacto na disponibilidade de 8,16 % .

Palavras-chave

Confiabilidade, Desempenho produtivo, Gestão da manutenção, Processos de mineração

Referências

Associação Brasileira de Normas Técnicas – ABNT. (1994). ABNT NBR 5462:1994: reliability and main maintainability: terminology (p. 37). Rio de Janeiro: ABNT.

Associação Brasileira de Normas Técnicas – ABNT (2014). ABNT NBR ISO 55000:2014: gestão de ativos: visão geral, princípios e terminologia. Rio de Janeiro: ABNT.

Barlow, R., & Hunter, L. (1960). Optimum preventive maintenance policies. Operations Research, 8(1), 90-100. http://dx.doi.org/10.1287/opre.8.1.90.

Barlow, R., & Proschan, F. (1987). Mathematical theory of reliability. Philadelphia: Society for Industrial and Applied Mathematics.

Blanchard, B. S., & Fabrycky, W. J. (1998). Systems engineering and analysis (3rd ed.). Englewood Cliffs: Prentice Hall.

Bokrantz, J., Skoogh, A., Berlin, C., Wuest, T., & Stahre, J. (2020). Smart maintenance: a research agenda for industrial maintenance management. International Journal of Production Economics, 224, 107547. http://dx.doi.org/10.1016/j.ijpe.2019.107547.

Campos, V. F. (2004). TQC: controle da qualidade total: no estilo japonês. Belo Horizonte: INDG Tecnologia e Serviços. Retrieved in 2023, October 16, from https://books.google.com.br/books?id=k13YRgAACAAJ

Carvalho, P. S. L., Silva, M. M., Rocio, M. A. R., & Moszkowicz, J. (2014). Minério de ferro. Rio de Janeiro: BNDES Setorial.

Caterpillar. (2022). Mining Trucks: 797F. Retrieved in 2023, October 16, from https://www.cat.com/pt_BR/products/new/equipment/off-highway-trucks/mining-trucks/18093014.html

Corrêa, H. L., & Corrêa, C. A. (2012). Administração de produção e operações: manufatura e serviços: uma abordagem estratégica. São Paulo: Atlas. Retrieved in 2023, October 16, from https://books.google.com.br/books?id=eptZlQEACAAJ

Doyen, L., & Gaudoin, O. (2004). Classes of imperfect repair models based on reduction of failure intensity or virtual age. Reliability Engineering & System Safety, 84(1), 45-56. http://dx.doi.org/10.1016/S0951-8320(03)00173-X.

Doyen, L., & Gaudoin, O. (2011). Modeling and assessment of aging and efficiency of corrective and planned preventive maintenance. IEEE Transactions on Reliability, 60(4), 759-769. http://dx.doi.org/10.1109/TR.2011.2171115.

Fernandes, R. S., Sousa, L. R. C., & Santos, T. L. (2021). Analysis, investigation and evaluation of quality management in the mining process: a case study on divergencies in iron ore stock deviations. Revista Produção Online, 21(3), 770-793. http://dx.doi.org/10.14488/1676-1901.v21i3.4252.

Fernandes, R. S., Rocha, T. R., Coelho, J. M., & Andrade, D. F. (2023a). Development of a measurement instrument to evaluate integrated management systems and differences in perception: an approach to item response theory and the quality manageme nt process. Production, 33, e20220069. http://dx.doi.org/10.1590/0103-6513.20220069.

Fernandes, R. S., Sousa, J. C. C., & Luz, R. M. N. (2023b). Integrated management analysis of production performance, maintenance, and PDCA cycle: a case study of the IPCC mining process. Revista Produção Online, 22(2), 2731-2762. http://dx.doi.org/10.14488/1676-1901.v22i2.4661.

Gackowiec, P., Podobińska-Staniec, M., Brzychczy, E., Kühlbach, C., & Özver, T. (2020). Review of key performance indicators for process monitoring in the mining industry. Energies, 13(19), 5169. http://dx.doi.org/10.3390/en13195169.

Gilardoni, G. L., & Colosimo, E. A. (2007). Optimal maintenance time for repairable systems. Journal of Quality Technology, 39(1), 48-53. http://dx.doi.org/10.1080/00224065.2007.11917672.

Gilardoni, G. L., Toledo, M. L. G., Freitas, M. A., & Colosimo, E. A. (2016). Dynamics of an optimal maintenance policy for imperfect repair models. European Journal of Operational Research, 248(3), 1104-1112. http://dx.doi.org/10.1016/j.ejor.2015.07.056.

Ishikawa, K. (1985). What is total quality control? The japanese way. Englewood Cliffs: Prentice-Hall. Retrieved in 2023, October 16, from https://books.google.com.br/books?id=59hTAAAAMAAJ

Kang, N., Zhao, C., Li, J., & Horst, J. A. (2016). A Hierarchical structure of key performance indicators for operation management and continuous improvement in production systems. International Journal of Production Research, 54(21), 6333-6350. http://dx.doi.org/10.1080/00207543.2015.1136082. PMid:29398722.

Kardec, A., & Nascif, J. (2009). Manutenção-função estratégica. Rio de Janeiro: Qualitymark.

Luz, A. B., & Lins, F. A. F. (2018). Introdução ao tratamento de minérios. Rio de Janeiro: CETEM/MCTIC.

Medeiros, L. A. A., Sousa, I. P., Fernandes, R. S., Luz, R. M. N., & Luz, M. A. L. (2022). Análise de confiabilidade para a redução do número de manutenções corretivas nos caminhões off-highway. In Anais do XLII Encontro Nacional de Engenharia de Produção (ENEGEP). São José dos Campos: ABEPRO. .. http://dx.doi.org/10.14488/ENEGEP2022_TN_ST_382_1888_44998.

International Council on Mining and Metals – ICMM. (2015). Critical control management: implementation guide. Retrieved in 2023, October 16, from https://books.google.com.br/books?id=kroRDAEACAAJ

Mohtasham, M., Mirzaei-Nasirabad, H., Askari-Nasab, H., & Alizadeh, B. (2021). Truck fleet size selection in open-pit mines based on the match factor using a MINLP model. Mining Technology, 130(3), 159-175. http://dx.doi.org/10.1080/25726668.2021.1919374.

Nakagawa, T. (1989). A replacement policy maximizing MTTF of a system with several spare units. IEEE Transactions on Reliability, 38(2), 210-211. http://dx.doi.org/10.1109/24.31107.

Oliveira, M. A. (2016). Sistema de gestão da manutenção baseada no grau de maturidade da organização no âmbito da manutenção (Tese de doutoramento). Universidade do Minho, Braga.

Osanloo, M., & Paricheh, M. (2020). In-pit crushing and conveying technology in open-pit mining operations: a literature review and research agenda. International Journal of Mining, Reclamation and Environment, 34(6), 430-457. http://dx.doi.org/10.1080/17480930.2019.1565054.

Pascual, R., Madariaga, R., Santelices, G., Godoy, D., & Droguett, E. L. (2016). A structured methodology to optimise throughput of production lines. International Journal of Mining, Reclamation and Environment, 30(1), 25-36. http://dx.doi.org/10.1080/17480930.2014.962235.

Qiao, G., Schlenoff, C., & Weiss, B. A. (2017). Quick positional health assessment for industrial robot prognostics and health management (PHM). In 2017 IEEE International Conference on Robotics and Automation (ICRA). New York: IEEE.. .. http://dx.doi.org/10.1109/ICRA.2017.7989214.

Rigdon, S. E., & Basu, A. P. (2000). Statistical methods for the reliability of repairable systems. New York: Wiley. Retrieved in 2023, October 16, from https://www.wiley.com/en-us/Statistical+Methods+for+the+Reliability+of+Repairable+Systems-p-9780471349419

Rocha, C. S., Cardoso, E. L. S. S., Fernandes, R. S., Branco, N. C. N. M., & Luz, R. M. N. (2021). Quality assessment of divergences causes in weighing copper ore at a mining company in the amazon region. International Journal of Developmental Research, 11(8), 49633-49639. http://dx.doi.org/10.37118/ijdr.22578.08.2021.

Shiba, S., & Graham, A. (1997). Tqm: quatro revoluções na gestão da qualidade. Porto Alegre: Bookman. Retrieved in 2023, October 16, from https://books.google.com.br/books?id=z27muAAACAAJ

Slack, N., Chambers, S., Johnston, R., & Betts, A. (2013). Gerenciamento de operações e de processos: princípios e práticas de impacto estratégico (2ª ed.). Porto Alegre: Bookman. Retrieved in 2023, October 16, from https://books.google.com.br/books?id=wLo3AgAAQBAJ

Toledo, M. L. G., Freitas, M. A., Colosimo, E. A., & Gilardoni, G. L. (2016). Optimal periodic maintenance policy under imperfect repair: a case study on the engines of off-road vehicles. IIE Transactions, 48(8), 747-758. http://dx.doi.org/10.1080/0740817X.2016.1147663.

Xenos, H. G. (2014). Gerenciando a manutenção produtiva: melhores práticas para eliminar falhas nos equipamentos e maximizar a produtividade. Nova Lima: Falconi Editora.

Zampolli, M. (2019). Gestão de ativos: guia para a aplicação da norma ABNT NBR ISO 55001 considerando as diretrizes da ISO 55002: 2018 (2ª ed.). Santiago: International Copper Association. Retrieved in 2023, October 16, from https://abcobre.org.br/wp-content/uploads/2021/04/gestao-de-ativos-guia-para-aplicacao-da-norma-abnt-nbr-iso-55001.pdf
 