Gestão & Produção
https://www.gestaoeproducao.com/article/doi/10.1590/1806-9649-2020v28e5264
Gestão & Produção
Artigo Original

The influence of risk management on the project portfolio success – proposal of a risk intensity matrix

Ricardo Luis Zanfelicce; Roque Rabechini Jr

Downloads: 1
Views: 877

Abstract

Abstract:: This article aims to understand how the risk management influences the project portfolio success. Two methodological approaches were selected in this research: a bibliometric survey followed by a case study. The object of study was the new products project portfolio of an organization from the industrial sector, manufacturer of durable goods. The findings revealed a low intensity of project portfolio risk management. This is aligned with the bibliometric survey results and with the evidence from the investigation performed on the case study unit. In order to evaluate the risk management influence over the portfolio success, this article proposes a matrix which suggests the risk management intensity associated with the project portfolio management processes. The proposed matrix application can be considered a contribution element to deepen the knowledge of the risk management influence on the project portfolio success.

Keywords

Risk management matrix, Portfolio risk management, Project portfolio success

Referências

Archambault, E., Campbell, D., Gingras, Y., & Lariviere, V. (2009). Comparing bibliometric statistics obtained from the Web of Science and Scopus. Journal of the American Society for Information Science and Technology, 60(7), 1320-1326. http://dx.doi.org/10.1002/asi.21062.

Archer, N., & Ghasemzadeh, F. (1999). An integrated framework for project portfolio selection. International Journal of Project Management, 17(4), 207-216. http://dx.doi.org/10.1016/S0263-7863(98)00032-5.

Artto, K. A., Kahkonen, K., & Pitkanen, P. (2000). Unknown soldier revisited: a story of risk management. Project Management Association Finland. Helsinki, Finland: PMA Finland.

Bardin, L. (2011). Análise de conteúdo. São Paulo: Edições 70.

Carlos, L., Serio, D., Serio, M. D. I., & Serio, M. D. I. (2017). Uma análise bibliométrica multifontes sobre a geração de valor ao acionista e a Gestão de Projetos, Programas e Portfólios. Revista de Gestão e Projetos - GeP, 8(2), 87-108. https://doi.org/10.5585/gep.v8i2.

Carvalho, M. M., & Rabechini, R., Jr. (2015). Impact of risk management on project performance: the importance of soft skills. International Journal of Production Research, 53(2), 321-340. http://dx.doi.org/10.1080/00207543.2014.919423.

Castro, H. G., & Carvalho, M. M. (2010). Gerenciamento do portfólio de projetos (PPM): estudos de caso. Produção, 20(3), 303-321. http://dx.doi.org/10.1590/S0103-65132010005000044.

Chapman, C., & Ward, S. (2004). Why risk efficiency is a key aspect of best practice projects. International Journal of Project Management, 22(8), 619-632. http://dx.doi.org/10.1016/j.ijproman.2004.05.001.

Cooper, R., & Edgett, S. (2010). Developing a product innovation and technology strategy for your business. Research Technology Management, 53, 33-40. http://dx.doi.org/10.1080/08956308.2010.11657629.

Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (1999). New product portfolio management: practices and performance. Journal of Product Innovation Management, 16(4), 333-351. http://dx.doi.org/10.1111/1540-5885.1640333.

Cooper, R., Edgett, S., & Kleinschmidt, E. (2001). Portfolio management for new products. New York: Basic Books.

Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (2002). Portfolio management: fundamental to new product success. In P. Belliveau, A. Griffin & S. Somermeyer (Eds.), The PDMA toolbook for new product development. New York: John Wiley & Sons.

Courtney, H., Kirkland, J., & Viguerie, P. (1997). Strategy under uncertainty. Harvard Business Review, 75(6), 67-79.

Reyck, B. D., Grushka-Cockayne, Y., Lockett, M., Calderini, S. R., Moura, M., & Sloper, A. (2005). The impact of project portfolio management on information technology projects. International Journal of Project Management, 23(7), 524-537. http://dx.doi.org/10.1016/j.ijproman.2005.02.003.

Elonen, S., & Artto, K. A. (2003). Problems in managing internal development projects in multi-project environments. International Journal of Project Management, 21(6), 395-402. http://dx.doi.org/10.1016/S0263-7863(02)00097-2.

Flanagan, R., & Norman, G. (1993). Risk management and construction. Victoria, Australia: Blackwell Science Pty Ltd.

Flyvbjerg, B. (2007). Policy and planning for large-infrastructure projects: problems, causes, cures. Environment and Planning. B, Planning & Design, 34(4), 578-597. http://dx.doi.org/10.1068/b32111.

Friese, S. (2012). Qualitative data analysis with Atlas.ti. London: SAGE Publications Ltd.

Ghasemzadeh, F., Archer, N., & Iyogun, P. (1999). A zero-one model for project portfolio selection and scheduling. The Journal of the Operational Research Society, 50(7), 745-755. http://dx.doi.org/10.1057/palgrave.jors.2600767.

Gil, A. C. (2011). Como elaborar projetos de pesquisa (5a. ed.). São Paulo: Atlas.

Hasna, A., & Raza, S. (2010). The status of project portfolio management practices adoption and awareness in Gulf Cooperation Counties: an empirical study. International Journal of Project Organisation and Management, 2(2), 174-192. http://dx.doi.org/10.1504/IJPOM.2010.033661.

Hill, W., & Jones, R. (1992). Strategic management theory: an integrated approach (2nd ed.). USA: Houghton Mifflin.

Hofman, M., Spalek, S., & Grela, G. (2017). Shedding new light on project portfolio risk management. Sustainability, 9(10), 1798. http://dx.doi.org/10.3390/su9101798.

Ikpaahindi, L. (1985). An overview of bibliometrics: its measurements, laws and their applications. Libri, 35(2), 163-176.

Jeffery, M., & Leliveld, I. (2004). Best practicies in IT Portfólio Management. MIT Sloan Management Review, 45(3), 41-49.

Jerbrant, A. (2014). A maturation model for project-based organizations - with uncertainty management as an ever-present multi-project management focus. South African Journal of Economic and Management Sciences, 17(1), 33-51.

Jonas, D., Kock, A., & Gemünden, H. G. (2010). The impact of portfolio management quality on project portfolio success. In Paper presented at EURAM 2010. Rom, Italy.

Jordão, R. V. D., Pelegrini, F. G., Jordão, A. C. T., & Jeunon, E. E. (2015). Fatores críticos na gestão de projetos: um estudo de caso numa grande empresa latino-americana de classe mundial. Gestão & Produção, 22(2), 280-294. http://dx.doi.org/10.1590/0104-530X1091-13.

Jerbrant, A., & Karrbom Gustavsson, T. (2013). Managing project portfolios: balancing flexibility and structure by improvising. International Journal of Managing Projects in Business, 6(1), 152-172. http://dx.doi.org/10.1108/17538371311291071.

Kerzner, H. (2009). Project management: a system approach to planning, scheduling, and controlling (10a ed). New Jersey: John Wiley and Sons.

Killen, C. P., Jugdev, K., Drouin, N., & Petit, Y. (2012). Advancing project and portfolio management research: applying strategic management theories. International Journal of Project Management, 30(5), 525-538. http://dx.doi.org/10.1016/j.ijproman.2011.12.004.

Khameneh, A., Sobhiyah, M. H., & Hosseini, S. H. K. (2016). Project portfolio management capability: the case of Iran’s power industry innovation projects. International Business Management, 10(12), 2329-2336.

Kock, A., Heising, W., & Gemünden, H. G. (2016). A contingency approach on the impact of front-end success on project portfolio success. Project Management Journal, 47(2), 115-129. http://dx.doi.org/10.1002/pmj.21575.

Kopmann, J., Kock, A., Killen, C. P., & Gemünden, H. G. (2015). Business case control in project portfolios: an empirical investigation of performance consequences and moderating effects. IEEE Transactions on Engineering Management, 62(4), 529-543. http://dx.doi.org/10.1109/TEM.2015.2454437.

Korhonen, T., Laine, T., & Martinsuo, M. (2014). Management Control of Project Portfolio Uncertainty: A Managerial Role Perspective. Project Management Journal, 45(1), 21-37. http://dx.doi.org/10.1002/pmj.21390.

Lee, K. C., Lee, N., & Li, H. (2009). A particle swarm optimization-driven cognitive map approach to analyzing information systems project risk. Journal of the American Society for Information Science and Technology, 60(6), 1208-1221. http://dx.doi.org/10.1002/asi.21019.

Markowitz, H. M. (1952). Portfolio selection. The Journal of Finance, 7(1), 77-91.

Marshall, C., & Rossman, G. B. (2006). Data collection methods. In C. Marshall & G. B. Rossman. Designing qualitative research (pp. 97-141). Thousand Oaks, Califórnia, EUA: Sage publications.

Martins, G. A., & Theóphilo, C. R. (2007). Metodologia da investigação científica para ciências sociais aplicadas. São Paulo: Editora Atlas SA.

Martinsuo, M., Korhonen, T., & Laine, T. (2014). Identifying, framing and managing uncertainties in project portfolios. International Journal of Project Management, 32(5), 732-746.

McFarlan, F. W. (1981). Portfolio approach to information systems. Harvard Business Review, 59(5), 142-150.

McFarlan, F. W. (1984). Information technology changes the way you compete. Harvard Business Review, 62(3), 98-103.

McNamara, C. (2006). General guidelines for conducting research interviews. Retrieved June 13, 2017, from http://managementhelp.org/businessresearch/interviews.htm

Meskendahl, S. (2010). The influence of business strategy on project portfolio management and its success: A conceptual framework. International Journal of Project Management, 28(8), 807-817. http://dx.doi.org/10.1016/j.ijproman.2010.06.007.

Mikkola, J. H. (2001). Portfolio management of ReD projects: implications for innovation management. Technovation, 21(7), 423-435. http://dx.doi.org/10.1016/S0166-4972(00)00062-6.

Moran, M. R., Souza, F. F. A., Boaventura, J. M. G., Marinho, B. L., & Fischmann, A. A. (2010). Alianças Estratégicas: uma análise bibliométrica da produção científica entre 1989 e 2008. Revista de Ciências da Administração, 12(27), 63-85. http://dx.doi.org/10.5007/2175-8077.2010v12n27p63.

Mu, S., Cheng, H., Chohr, M., & Peng, W. (2014). Assessing risk management capability of contractors in subway projects in mainland China. International Journal of Project Management, 32(3), 452-460. http://dx.doi.org/10.1016/j.ijproman.2013.08.007.

Neumeier, A., Radszuwill, S., & Garizy, T. Z. (2018). Modeling project criticality in IT project portfolios. International Journal of Project Management, 36(6), 833-844.

Olsson, R. (2008). Risk management in a multi‐project environment. International Journal of Quality & Reliability Management, 25(1), 60-71. http://dx.doi.org/10.1108/02656710810843586.

Padovani, M., & Carvalho, M. M. (2016). Integrated PPM Process: scale development and validation. International Journal of Project Management, 34(4), 627-642.

Petit, Y. (2012). Project portfolios in dynamic environments: organizing for uncertainty. International Journal of Project Management, 30(5), 539-553. http://dx.doi.org/10.1016/j.ijproman.2011.11.007.

Prasad, S., & Tata, J. (2005). Publication patterns concerning the role of teams/groups in the information systems literature from 1990 to 1999. Information & Management, 42(8), 1137-1148. http://dx.doi.org/10.1016/j.im.2005.01.003.

Project Management Institute. (2017a). A guide to the project management body of knowledge (PMBOK ® Guide) (6th ed.). Newtown Square, PA: PMI.

Project Management Institute. (2017b). The standard for portfolio management (4th ed.) Newtown Square, PA: PMI.

Rank, J., Unger, B. N., & Gemünden, H. G. (2015). Preparedness for the future in project portfolio management: the roles of proactiveness, riskiness and willingness to cannibalize. International Journal of Project Management, 33(8), 1730-1743.

Raz, T., Shenhar, A. J., & Dvir, D. (2002). Risk management, project success, and technological uncertainty. R & D Management, 32(2), 101-109. http://dx.doi.org/10.1111/1467-9310.00243.

Redmill, F. (2002). Risk analysis: a subjective process. Engineering Management Journal, 12(2), 91-96.

Sanchez, H., Robert, B., & Pellerin, R. (2008). A project portfolio risk-opportunity identification framework. Project Management Journal, 39(3), 97-109. http://dx.doi.org/10.1002/pmj.20072.

Shenhar, A. J., Dvir, D., Levy, O., & Maltz, A. C. (2001). Project success: A multidimensional strategic concept. Long Range Planning, 34(6), 699-725. http://dx.doi.org/10.1016/S0024-6301(01)00097-8.

Shenhar, A. J., & Dvir, D. (2007). Why your business success depends on projects—excerpted from reinventing project management: the diamond approach to successful growth and innovation. Boston, Massachusetts: Harvard Business Press.

Small, H. (2003). Paradigms, citations, and maps of science: a personal history. Journal of the American Society for Information Science and Technology, 54(5), 394-399. http://dx.doi.org/10.1002/asi.10225.

Teller, J., Unger, B. N., Kock, A., & Gemünden, H. G. (2012). Formalization of project portfolio management: the moderating role of project portfolio complexity. International Journal of Project Management, 30(5), 596-607. http://dx.doi.org/10.1016/j.ijproman.2012.01.020.

Teller, J. (2013). Portfolio risk management and its contribution to project portfolio success: an investigation of organization, process and culture. Project Management Journal, 44(2), 36-51. http://dx.doi.org/10.1002/pmj.21327.

Teller, J., & Kock, A. (2013). An empirical investigation on how portfolio risk management influences project portfolio success. International Journal of Project Management, 31(6), 817-829. http://dx.doi.org/10.1016/j.ijproman.2012.11.012.

Teller, J., Kock, A., & Gemunden, H. G. (2014). Risk management in project portfolios is more than managing project risks: a contingency perspective on risk management. Project Management Journal, 45(4), 67-80. http://dx.doi.org/10.1002/pmj.21431.

Wang, Q., Zeng, G., & Tu, X. (2017). Information technology project portfolio implementation process optimization based on complex network theory and entropy. Entropy (Basel, Switzerland), 19(6), 287. http://dx.doi.org/10.3390/e19060287.

Ward, S. C., & Chapman, C. B. (1991). Extending the use of risk analysis in project management. International Journal of Project Management, 9(2), 117-123. http://dx.doi.org/10.1016/0263-7863(91)90071-3.

Ward, S., & Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21(2), 97-105. http://dx.doi.org/10.1016/S0263-7863(01)00080-1.

Wideman, M. (1992). Project and program risk management: a guide to managing project risks and opportunities. Newton Square. Pennsilvania, USA: Project Management Institute.

Yamakawa, E. K., Sousa-Zomer, T. T., Cauchick-Miguel, P. A., & Killen, C. P. (2018). R&D portfolio management practices in Brazilian electric power utilities. Benchmarking, 25(6), 1641-1655. http://dx.doi.org/10.1108/BIJ-10-2016-0159.

Yin, R. K. (2015). Estudo de caso: planejamento e métodos (5a. ed.). Porto Alegre: Bookman.

Zupic, I., & Čater, T. (2015). Bibliometric methods in management and organization. Organizational Research Methods, 18(3), 429-472. http://dx.doi.org/10.1177/1094428114562629.

Zwikael, O., & Ahn, M. (2011). The effectiveness of risk management: an analysis of project risk planning across industries and countries. Risk Analysis, 31(1), 25-37. http://dx.doi.org/10.1111/j.1539-6924.2010.01470.x. PMid:20723146.
 